Rooppur begins second trial electricity supply to national grid

Online Desk:

Pabna: The Rooppur Nuclear Power Plant began its second trial supply of electricity to the national grid at 10:20am on Monday, as part of the ongoing testing of the country’s first nuclear power facility.

Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, said around 300-350MW of electricity would be supplied to the national grid on a trial basis for 10-24 hours.

During this period, necessary technical tests will be conducted on the plant’s power generation system and its integrated operation with the national grid, he said.

The plant first began supplying around 350MW of electricity to the national grid on a trial basis on 17 November at 3:16pm. The unit was disconnected after about eight and a half hours of supply for further technical tests.

Monday’s second trial grid connection marks the continuation of the testing process.

The Rooppur plant, built with Russian technical and financial backing at Ishwardi in Pabna, has two units, each with a generation capacity of 1,200MW, taking its total capacity to 2,400MW.

Under the agreement with the Russian contractor, the first unit will undergo around 10 months of trial operation before beginning commercial electricity supply at full capacity.