Old Brahmaputra River dredging restores water flow: Boosts agriculture, navigation

The Bangladesh Inland Water Transport Authority (BIWTA), under the Ministry of Shipping, is continuing the implementation of the project titled “Navigability Improvement and Restoration of the Old Brahmaputra, Dharla, Tulai and Punarbhaba Rivers (1st Revised)”. As part of the project, dredging activities are being carried out along the Old Brahmaputra River, which flows through Gazipur’s Kapasia Tok area and passes through several upazilas of Kishoreganj, Mymensingh, Sherpur, Jamalpur and Gaibandha districts.

According to project authorities, the consultancy firm Institute of Water Modelling (IWM) is supervising dredging operations along a 225-kilometre stretch of the river. Dredging work is currently underway across the entire route, with 96 dredgers engaged in the operation.

A recent field visit revealed that dredging has significantly improved the river’s flow, particularly in Mymensingh and Kishoreganj districts. Increased water flow has enabled the movement of small vessels and sand-carrying cargo ships. The restored water availability is also benefiting agricultural activities, helping irrigate farmlands and contributing to better crop production. Local residents reported that the river has become a more suitable habitat for fish and other aquatic species, strengthening the region’s fisheries resources.

The Old Brahmaputra River plays a crucial role in Bangladesh’s agriculture, fisheries and inland water transport systems. BIWTA officials said they are working relentlessly to restore and maintain the river’s navigability and ecological balance.

Local residents living along the riverbanks welcomed the dredging initiative, stating that water flow has increased noticeably following the excavation work. However, they emphasized the need for regular maintenance dredging, as the river tends to silt up every year. They also pointed out that riverbank protection measures are needed in several locations. Some residents suggested that dredged sand could be provided free of charge to local landowners to accelerate project implementation and called for stronger action against illegal sand extraction.

Engineers working for IWM noted that the project has faced several challenges, including a shortage of suitable disposal sites for dredged materials, heavy sedimentation across much of the riverbed, delays in clearing disposal-point dykes, boundary demarcation disputes and various forms of local resistance. They reported incidents of arson, vandalism and attacks on dredgers, pipelines and project staff, which have hindered progress.

“The project was taken in 2019 at a cost of Tk 2100 crore targeting to complete it by 2027. But, it wouldn’t be possible to complete within the stipulated period as various complication pushed the project work delayed. So, it is likely to be extended the project one more year,” Project Director Saidur Rahman told The Morning Bell.

BIWTA officials stated that the Old Brahmaputra River had never undergone dredging before this project. Of the 225-kilometre project area, dredging is currently active along approximately 210 kilometres. They further explained that at Sannyasichar (offtake) in Fulchhari Upazila of Gaibandha District, the river remains disconnected from the Jamuna River for nearly eight months each year. Dredging activities in the area were reportedly obstructed by local resistance for around five years. At present, dredging work is continuing with support from the Bangladesh Army.

Officials believe that reconnecting the Old Brahmaputra with the Jamuna River through dredging will help restore the river’s vitality. They noted that the river frequently changes its course and is highly prone to sedimentation, making annual maintenance dredging essential to keep the waterway functional. BIWTA expressed hope that cooperation from local administrations, elected representatives and community leaders would facilitate the successful completion of the project and ensure the long-term sustainability of the river.